Home MenuMcCurdy Road Stormwater Improvements
Project Description
There is a concern of flooding during high rain events from a culvert pipe under McCurdy Road. In order to alleviate potential water concerns, a 30 inch catch basin will be installed with 420 linear feet of culvert pipe to redirect water flow.
Project Updates
- Project was Completed on July 11th, 2022
- Purchase Order entered 04/09/2022
- Scheduled to be completed in May 2022
Project Location
775 & 779 McCurdy Road, White House, Tennessee
Project Impacts
Residents at 775 & 779 McCurdy Road will have a visual inconvenience as infrastructure is being installed.
There will be an increase of motor vehicles traffic on McCurdy Road.
Latest Updates
Estimates have been received and are currently being reviewed for approval. P.O. # 2708 was entered on 04/09/2022
Budget
PHASE | COST |
Total Budget | $20,315.00 |
Funding Source | Stormwater Fees MANDATED BY CONGRESS |
Total Cost | $23,212.00 |
Schedule
PHASE | Estimated Start Date | Forecast Completion | Actual Completion |
Planning & Approval | 04/15/2021 | 04/11/2022 | 04/09/2022 |
Design Development | 07/14/2021 | 09/28/2021 | 04/05/2022 |
Construction | 05/14/2022 | 06/01/2022 | 17/11/2022 |