Project Description

There is a concern of flooding during high rain events from a culvert pipe under McCurdy Road. In order to alleviate potential water concerns, a 30 inch catch basin will be installed with 420 linear feet of culvert pipe to redirect water flow.

Project Updates

  •  Project was Completed on July 11th, 2022
  • Purchase Order entered 04/09/2022
  • Scheduled to be completed in May 2022

Project Location

775 & 779 McCurdy Road, White House, Tennessee 

Project Impacts

Residents at 775 & 779 McCurdy Road will have a visual inconvenience as infrastructure is being installed.

There will be an increase of motor vehicles traffic on McCurdy Road.

Latest Updates 

Estimates have been received and are currently being reviewed for approval. P.O. # 2708 was entered on 04/09/2022

Budget 

PHASE   COST
 Total Budget   $20,315.00
 Funding Source   Stormwater Fees MANDATED BY CONGRESS
 Total Cost $23,212.00

 

Schedule 

PHASE Estimated Start Date    Forecast Completion   Actual Completion 
 Planning & Approval  04/15/2021   04/11/2022  04/09/2022
 Design Development   07/14/2021  09/28/2021  04/05/2022
 Construction   05/14/2022  06/01/2022  17/11/2022

 

Supporting Materials