Project Description
PRIMARY PROJECT SCOPE:
During discussions about stormwater coordination for the City of White House various drainage issues near Wilkinson Lane were presented. These issues include improper backwater and flows at the intersection of Wilkinson Lane and Hickerson Drive, roadway overtopping at the intersection of Wilkinson Lane and Meadow Court, and multiple residential drainage issues near Shady Lane and Meadow Court. CSR Engineering was tasked to further observe and analyze the stormwater infrastructure where drainage issues are occurring.
Project Updates
- Purchase Orders have been submitted and approved
- Ordering Infrastructure has begun
- All pipe and miscellaneous infrastructure have been installed
- Trees were trimmed and/or removed on Hickerson Dr. 11/21/2022 – 11/23/2022
- Waiting on safety drain steel pipe grates. Currently on backorder.
Project Location
Wilkinson Lane, Hickerson Drive, Shady Lane, and Meadow Court
Project Impacts
There will be an increase of motor vehicle traffic at construction location and minor noise irritation for residents
Latest Updates
- Stormwater in conjunction with Public Works will coordinate installation
- Infrastructure has started to be ordered on 4/05/2022
Budget
PHASE |
COST |
Actual |
Total Budget |
$150,000.00 |
approximately $75,000 |
Funding Source |
Stormwater Enterprise Fund |
N/A |
Schedule
PHASE |
Estimated Start Date |
Forecast Completion |
Actual Completion |
Planning & Approval |
05/01/2020 |
07/01/2021 |
08/19/2021 |
Design Development |
07/01/2020 |
08/01/2020 |
02/16/2021 |
Delivery of Tractor and Infrastructure |
06/06/2022 |
06/09/2022 |
06/09/2022 |
Construction | 06/14/2022 | 07/01/2022 | 11/23/2022 |