Project Description
PRIMARY PROJECT SCOPE:
- The project generally consists of demolition/removal of an existing stormwater pipe network to allow for the project grading and new pipe installation
- All necessary planning of project installation to accommodate stormwater flows for the duration of the pipe replacement
- Installation of new 29”x45” elliptical RCP pipes
- Installation of new catch basins at the roadway and yard inlet interfaces
- Installation of appropriate upstream and downstream end walls
- All other associated miscellaneous details and ancillary items detailed in plans
- Protect, repair or replace all signage, fences, surface (roads and lawns) material and similarly affected existing infrastructure as may be affected during the construction of the primary project and not intended to be damaged by the project
Project Updates
- Bid Opening on August 9th 2021
- August 19th, 2021 went to the Board of Mayor Alderman for approval
- Awarded to Scott & Ritter, Inc. on August 20th, 2021
- Mobilizing started in January of 2022 – Infrastructure & Machinery
- Utilities conflicts (Water, Sewer, Fiber, & Gas) were moved in late February early March
- March 16, 2022 all infrastructure was installed
- Scott & Ritter started grading and laid seed and straw. The ground is to saturated for finish grade. Scott & Ritter will come back in a few months to finish all the grade work. Affected residents have been notified.
Project Location
Springbrook Subdivision
Project Impacts
Exposing a gas main, sewer, water & fiber by hydro excavation, and acquisition of pipe delayed a portion of the project.
There will be an increase of motor vehicle traffic at construction location and minor noise irritation for residents
Latest Updates
- All infrastructure has been installed.
- Final Grade will be completed once the dry season arrives.
- Scott & Ritter emailed on 5/23/2022 stating that all final grading has been completed
Budget
PHASE |
COST |
Actual |
Total Budget |
$270,000.00 |
$366,165.99 |
Funding Source |
Stormwater Enterprise Fund |
N/A |
Schedule
PHASE |
Estimated Start Date |
Forecast Completion |
Actual Completion |
Planning & Approval |
05/01/2020 |
07/01/2021 |
8/19/2021 |
Design Development |
07/14/2020 |
01/28/2021 |
02/16/2021 |
Construction |
01/01/2022 |
2/30/2022 |
6/30/2022 |
Full Completion | N/A | N/A | 6/30/2022 |