Springbrook Stormwater Mitigation

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

Project Description

PRIMARY PROJECT SCOPE:

  • The project generally consists of demolition/removal of an existing stormwater pipe network to allow for the project grading and new pipe installation
  • All necessary planning of project installation to accommodate stormwater flows for the duration of the pipe replacement
  • Installation of new 29”x45” elliptical RCP pipes
  • Installation of new catch basins at the roadway and yard inlet interfaces
  • Installation of appropriate upstream and downstream end walls
  • All other associated miscellaneous details and ancillary items detailed in plans
  • Protect, repair or replace all signage, fences, surface (roads and lawns) material and similarly affected existing infrastructure as may be affected during the construction of the primary project and not intended to be damaged by the project

Project Updates

  • Bid Opening on August 9th 2021
  • August 19th, 2021 went to the Board of Mayor Alderman for approval
  • Awarded to Scott & Ritter, Inc. on August 20th, 2021
  • Mobilizing started in January of 2022 – Infrastructure & Machinery
  • Utilities conflicts (Water, Sewer, Fiber, & Gas) were moved in late February early March
  • March 16, 2022 all infrastructure was installed
  • Scott & Ritter started grading and laid seed and straw. The ground is to saturated for finish grade. Scott & Ritter will come back in a few months to finish all the grade work. Affected residents have been notified.

Project Location

Springbrook Subdivision

Project Impacts

Exposing a gas main, sewer, water & fiber by hydro excavation, and acquisition of pipe delayed a portion of the project.

There will be an increase of motor vehicle traffic at construction location and minor noise irritation for residents

Latest Updates

  • All infrastructure has been installed.
  • Final Grade will be completed once the dry season arrives. 
  • Scott & Ritter emailed on 5/23/2022 stating that all final grading has been completed 

Budget   

PHASE

COST

Actual

Total Budget

$270,000.00

$366,165.99

Funding Source

Stormwater Enterprise Fund

N/A

 

Schedule

PHASE

Estimated Start Date

Forecast Completion

Actual Completion

Planning & Approval

05/01/2020

07/01/2021

8/19/2021

Design Development

07/14/2020

01/28/2021

02/16/2021

Construction

01/01/2022

2/30/2022

6/30/2022

 Full Completion  N/A  N/A  6/30/2022