Southern Wastewater Force Main Replacement

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Project Description

A new Southern Force-Main would facilitate increased sanitary sewer flow capacities and allow for additional growth in the south eastern corridor within the City of White House.  The new force-main to be designed will be a 20-inch line, and will ultimately replace the 12-inch line currently in the same corridor.

 

Project Updates

  • Purchase Order entered 05/25/2021 for Design
  • 2/01/2022 boring started under I-65
  • The bore under I-65 with casing is complete.
  • 5/14/2022 Contractor exposed gas line at the corner of State Road 76 and Loves Lane
  • 6/06/2022 is the anticipated start date for the 76 Bore
  • Phase 1 of the project has been completed 
  • Phase 2 was awarded on August 8th, 2022 to Twin States in the amount of $989,836.00
  • Twin States has ordered all pipe and parts necessary for Phase II
  • Boring I-65 and 76 are complete
  • Phase 3 is going out to Bid sometime in the beginning of next year 2023
  • Phase 3 will run from DEE CEE Ct to Industrial Drive into the wastewater treatment facility
  • All utilities conflicts have been identified in Phase 3 with hydro-excavating. 

Project Location

The Force Main will ultimately run from the Wastewater Treatment Facility on 725 Industrial Drive across town to Tyree Springs into a lift station to be located in Dorris Farms at Willow Springs. 

Project Impacts

Exposing a gas main by hydro excavation, acquisition of pipe and valves has delayed a portion of the project.

There will be an increase of motor vehicle traffic at construction locations

Latest Updates

  •  Progress is going well. Lead times on valves have been a slight issue.

Budget   

PHASE 1

COST

Total Budget (Estimated for all phases)

Total for all Phases $7,500,000.00

 Actual Budget for Phase 1   $1,777,619.64

Funding Source

Wastewater Enterprise Fund & American Recovery Fund

 PHASE 2  COST
 Estimated Amount  $938,000.00
 Awarded Bid Amount  $989,836.00
 PHASE 3  COST
Plans have been approved TBD

 

Schedule

ALL PHASES

Estimated Start Date

Forecast Completion

Actual Completion

Planning & Approval

04/20/2021

05/20/2021

7/01/2021

Design Development

07/14/2021

05/28/2022

 

Construction Phase 1 of 4

02/01/2022

06/30/2022

 

 Gas Line Exposure  02/23/2022  3/23/2022  5/14/2022